Start with the hours you have.

Use a weekly capacity forecast to decide what to commit to and what you’ll revisit.

Subtract recurring work first

Start with hours from the people available this week. If that leaves 24 team hours, and six hours go to meetings and recurring support, you have 18 hours for project work. Keep estimates in the same units across the list.

Put commitments and prerequisites together

If you have to fix a signup error, the team may still need three hours to reproduce it before starting the seven-hour fix. Name both. If required work exceeds the week, decide which obligation can move, change scope, or get help before adding anything else.

Check what changes if you lose time

Try twelve project hours in place of eighteen. A three-hour prerequisite and seven-hour fix still fit. A five-hour email test may have to wait. Write down which trade-off the team agreed to so the deferred work has a clear reason.

How the planner orders work

It includes required work and its prerequisites first, even when commitments exceed capacity. It considers everything else from highest priority down. For equal priorities it considers the shorter estimate first. It counts shared prerequisites once and can schedule a smaller task that fits when an earlier task is too large.